Timmins Mountjoy Solar
Development
Project

a proposed 30.01 MWdc solar energy generation facility in the Township of Timmins.

Project Overview

The Timmins Mountjoy Solar Project’s proposed design capacity is 30.01 MWdc and is located outside the Township of Timmins, ON. The municipal address is 715 Dalton Road, Timmins, Ontario. Timmins received its Municipal Support Resolution from The Township of Timmins to submit a proposal for IESO LT2(e-1) RFP.

The Project will seek local farmers to graze their sheep herds, thereby improving land biodiversity through natural weed control. Bee hives will be added to the land enhancing pollination, improving soil health, and increasing crop yield.

Project Benefits

  • Provide annual tax revenue to local and provincial governments over the life of the Project.
  • Provides community benefits revenue to local government and First Nation land the Project is located on.
  • Create local employment and contracting opportunities during the development, construction, operation, and decommissioning phases of the Project.
  • Increase revenue to local businesses due to economic spinoff from Project activities.
  • Produce emission-free electricity that will both increase energy security and displace generation from fossil fuels, thereby reducing greenhouse gas emissions.
Location

Timmins, ON

Size

111 acres

Zoning

Rural

Capacity

30.01 MWdc

Connection

Interconnection to two Hydro One 27.6 kV feeders near site.

Land

Generally flat with woodlands and watercourses to the north beyond site location.

Other

5MWac proposed as an agrivoltaics project

Public Open House

Two Open Houses will occur in 2026 with event details made public through local media outlets

Date:

July 21, 2025
6 PM - 8 PM

Location:

Perth Legion,
26 Beckwith St E. Perth, ON

Food and Refreshments Provided.

Location

715 Dalton Road, Timmins, Ontario

Timmins-Map

Timeline / Key Activities

  • Q4 2024 - Q2 2025

    Project Identification

    • Land Lease
    • Interconnection assessment
    • Technical due diligence
    • Environmental impact assessment
  • Q2 2025 - Q4 2025

    Stakeholder Engagement

    • Current Phase for Sitka
    • Consultation with municipality and neighbours’
    • Indigenous Community Consultation
  • Q2 2025 - Q3 2025

    Permitting

    • IESO LT2 Submission
    • Municipal Support Letter
    • Confirm Local Indigenous Support
  • Q2 2026

    IESO Procurement

    • IESO contract award
Current focus is on preparing the projects in advance of a
potential award in April 2026

Anticipated Long term timeline

  • 2024

    Land Lease

    • Permitting Review

    • Municipal Support

    • Interconnection assessment

  • 2025 - 2026

    IESO Procurement

    • Proven process ensures a smooth process

  • 2025 - 2026

    Engineering, Design & Approvals

    • IESO contract award

    • Municipal Permitting Approvals

    • Design & Construction

  • 2026 - 2028

    Construction

    • Solar array is installed

    • Project connected to existing distribution lines

     

  • 2029 - 2049+

    Commercial Operations

    • Remote monitoring

    • Annual Maintenance

  • 2051+

    Decomissioning

    • Equipment is removed

    • Land fully remediated

    • Opportunity for re-commissioning

Development Team

sitkalogo
Sitka Power - Developer, owner & operator

Sitka is led by an experienced management team, who are qualified, responsible developers, owners and operators of solar, wind, run-of river hydro, and battery energy storage assets. Sitka is backed by a dedicated private infrastructure fund.​

Sikta owns and operates 6 solar, 1 wind, and 1 battery project in Ontario, 1 solar project in Saskatchewan, 3 run-of-river hydro projects and 1 regulated utility system in British Columbia.

RECONCEPT CANADA – DEVELOPMENT PARTNER

reconcept Canada is a renewable energy developer and investor, part of the reconcept Group, headquartered in Hamburg, Germany, with offices in Berlin, Helsinki, and Toronto. Since 1998, reconcept has been developing and financing sustainable energy projects, including solar, wind, hydro, and tidal power.

What is Agrivoltaics?

Definition

Dual use of land for agriculture and solar photovoltaic (PV) electricity generation.

Objective

Generate renewable energy while enhancing agricultural productivity.

Configuration Types

On Farm Benefits

  • Natural vegetation control
  • Improved water retention
  • Increased biodiversity and soil health
  • Reliable revenue for farms
  • Greater Community Acceptance

COntact Information

Cory st. croix

Project downloads

Suite 1050, 639 5th Ave SW
Calgary, AB T2P 0M9

866-GO-SITKA | 866-467-4852
info@sitka-power.ca

Sitka Power respectfully acknowledges and pays tribute to the traditional territories of the peoples of Treaty 7, which include the Blackfoot Confederacy (comprised of the Siksika, the Piikani, and the Kainai First Nations), the Tsuut’ina First Nation, and the Stoney Nakoda (including Chiniki, Bearspaw, and Goodstoney First Nations), and to the Métis Nation of Alberta (Districts 5 and 6), on which our offices are located.